home renovation project in singapore hdb bto with electrical works, flooring, painting

Home Renovation: How Long To Renovate Your House?

When you renovate your home, you embark on an exciting journey, but one of the first questions every homeowner asks is: "How long will my renovation take?"

Whether you're moving into a new BTO flat, upgrading a resale HDB, renovating a condominium, or refreshing a landed property, understanding the renovation timeline helps you plan your move-in date, budget, and expectations.

In Singapore, a typical flat renovation can take anywhere from 6 weeks to 16 weeks, depending on the scope of work, property type, and customisation involved.

In this guide, we'll break down the renovation process and explain what factors can affect your renovation timeline.

Typical Renovation Timeline in Singapore

Renovation Type Estimated Duration
Minor Renovation 2 – 4 weeks
New BTO Flat Renovation 6 – 10 weeks
Resale HDB Renovation 8 – 12 weeks
Condominium Renovation 8 – 14 weeks
Extensive Home Renovation 12 – 16 weeks or more

The actual duration depends on the complexity of the design, custom carpentry requirements, material lead times, and permit approvals.

Stage 1: Planning and Design (1 – 4 Weeks)

Before any hacking or installation begins, homeowners need to finalise their renovation plans.

During this stage, your interior designer or renovation contractor will:

  • Understand your lifestyle needs

  • Create space planning layouts

  • Develop design concepts

  • Select materials and finishes

  • Prepare quotations

  • Finalise the renovation contract

The more decisions that are made upfront, the smoother the renovation process will be.

Pro Tip

Avoid changing your design midway through the renovation. When you renovate your house, design revisions often result in delays, additional costs, and scheduling conflicts.

Stage 2: Permit Applications and Approvals (3 – 14 Days)

Certain renovation works in Singapore require approval before work can commence.

Examples include:

  • HDB hacking permits

  • Bathroom waterproofing works

  • Electrical upgrades

  • Structural modifications

For HDB flats, permits are typically submitted through HDB-approved contractors.

While approval times are generally quick, it is important to factor them into your renovation schedule.

Stage 3: Demolition and Hacking Works (3 – 7 Days)

Once approvals are obtained, the renovation begins with demolition.

This may include:

  • Removing existing flooring

  • Hacking walls

  • Dismantling old cabinets

  • Removing bathroom fixtures

  • Clearing unwanted built-ins

Resale flats often require more demolition work than new BTO units, which can add several days to the overall timeline.

Stage 4: Masonry, Flooring and Tiling Works (2 – 4 Weeks)

This stage lays the foundation for your new home.

Common works include:

  • Constructing feature walls

  • Building platforms

  • Installing floor tiles

  • Bathroom tiling

  • Kitchen wall tiling

  • Screeding and levelling

Tiling is one of the most time-consuming parts of renovation because proper curing and drying time is necessary to ensure long-lasting results.

Stage 5: Electrical and Plumbing Works (1 – 2 Weeks)

After major construction works are completed, electricians and plumbers begin installing essential services.

This includes:

  • New power points

  • Lighting installation

  • Water supply lines

  • Kitchen appliances connections

  • Bathroom fittings

  • Network and data points

Good coordination between trades is crucial to avoid delays at this stage.

More abour our Warranty.

Stage 6: Custom Carpentry Fabrication (3 – 6 Weeks)

Custom-built carpentry is often the longest lead-time item in a renovation project.

Examples include:

  • Kitchen cabinets

  • Wardrobes

  • TV consoles

  • Study tables

  • Shoe cabinets

  • Vanity cabinets

Most carpentry is fabricated off-site while other renovation works continue.

Homeowners who choose highly customised cabinetry, premium finishes, or imported accessories may experience longer lead times.

More about Oppolia by HomeShake

Stage 7: Installation of Carpentry and Fixtures (1 – 2 Weeks)

Once fabrication is completed, installation begins.

This stage includes:

  • Kitchen cabinet installation

  • Wardrobe installation

  • Countertop fitting

  • Bathroom vanity installation

  • Internal accessories and fittings

Countertop materials such as quartz, sintered stone, and natural stone may require additional site measurements and fabrication time before final installation.

More about Kitchen Renovation in Singapore

Stage 8: Painting, Touch-Ups and Cleaning (3 – 7 Days)

The final stage transforms the renovation site into a move-in-ready home.

Works include:

  • Painting walls and ceilings

  • Silicone touch-ups

  • Defect rectification

  • Deep cleaning

  • Final inspections

A thorough quality check ensures all items are completed before handover.

What Can Delay a Renovation Project?

Several factors can extend renovation timelines:

1. Design Changes During Construction

Changing layouts, materials, or carpentry specifications after work has started can significantly impact schedules.

2. Custom-Made Furniture and Imported Materials

Special-order items may have lead times ranging from several weeks to a few months.

3. Permit and Management Approvals

Condominiums often require management approval before renovation work begins.

4. Material Availability

Popular tiles, countertops, appliances, and fixtures can occasionally experience stock shortages.

5. Unexpected Site Conditions

Older resale flats may reveal hidden issues such as water seepage, damaged wiring, or uneven floors that require additional rectification work.

How to Speed Up Your Renovation

Homeowners can help reduce renovation delays by:

  • Finalising designs early

  • Choosing materials before work starts

  • Confirming appliance specifications upfront

  • Working with an experienced renovation partner

  • Avoiding last-minute changes

Clear communication and proper project management often make the biggest difference in keeping renovations on schedule.

Wooden wardrobe installation in a room with tools and materials on the floor. Carpenter Singapore installation a Closet with Oppolia Carpentry in Landed Property with Drywall and False Ceiling and Pants Rack and BLUM Drawers.

So, How Long Should You Expect?

For most homeowners in Singapore:

  • BTO flats: 6 to 10 weeks

  • Resale HDB flats: 8 to 12 weeks

  • Condominiums: 8 to 14 weeks

  • Major renovations: 12 to 16 weeks or longer

Every home is unique, but a realistic timeline allows you to plan your move, furniture purchases, and living arrangements with confidence.

Renovate with Confidence with HomeShake

At HomeShake, we believe that a successful renovation is not just about beautiful design—it's also about efficient project management and transparent communication.

Our team works closely with homeowners throughout every stage of the renovation journey, from design planning and material selection to custom carpentry and final handover. Whether you're renovating a new BTO, resale HDB, condominium, or landed property, we help ensure your project stays on track and delivers the home you've always envisioned.

Contact HomeShake today to discuss your renovation plans and receive a personalized consultation.

People visiting a showroom with kitchen and bathroom fixtures, featuring Oppolia brand.

Let's Discuss Your Project

Book an Appointment with our Design Consultants to get your Free Quotation

Singapore Carpentry Guide | 2026 Edition

A resource for homeowners, interior designers and renovators looking for expert advice on carpentry, kitchen cabinets, wardrobes, bespoke furniture, materials, renovation and woodworking in Singapore.
Landed house in Singapore where carpenters a drilling a decorative panel with moulding on a kitchen cabinet

How to Choose a Carpenter in Singapore

Learn how to compare quotations, materials, workmanship, project management, installation capabilities and after-sales support.
Display of various colour samples in oppolia carpentry showroom in singapore

Carpentry Materials & Construction

Learn how hardware, finishes, formaldehyde emissions, edge finishing and construction quality affect the durability, safety and performance of built-in furniture.
oppolia singapore wardrobe internal melamine finish

Wardrobes & Built-in Storage

Learn how to plan built-in wardrobes and custom storage solutions that maximise space and improve organisation in Singapore homes
oppolia kitchen cabinet sink undermount gasket singapore carpentry homeshake

Kitchen Carpentry

Understand the key considerations when choosing kitchen carpentry in Singapore, including kitchen cabinets, countertops, hardware, finishes and water-resistant construction.
singapore carpenter making bespoke custom made furniture desk in solid wood in homeshake's workshop

Bespoke & Solid Wood Furniture

Learn how made-to-measure craftsmanship can create durable, personalised furniture that suits your home, lifestyle and interior design.
flagship showroom oppolia singapore kitchen wardrobe door vanity

HomeShake's Carpentry Expertise

Learn how experienced carpenters and advanced cabinetry systems can support HDB, BTO, condominium and landed-home renovations across Singapore.

Explore HomeShake's Carpentry & Renovation Services

Visit the HomeShake showroom in Kaki Bukit to compare materials, finishes and cabinetry options.
TV Consoles & Feature Walls - HomeShake
TV Consoles & Feature Walls
Oppolia Wardrobes - HomeShake Formaldehyde-free Closet with Blum hardware for for Singapore homeowners, renovation projects.
Wardrobes
Kitchen Accessories from HomeShake Singapore with Oppolia Carpentry for Integrated, Smart, Practical Kitchens
Kitchen Accessories
Oppolia Bathroom Vanity Cabinets - HomeShake - formaldehyde-free, low VOC,moisture resistant carpentry for Singapore
Bathroom Vanity Cabinets
Modern kitchen counter with sink and stove, featuring Oppolia brand.

Oppolia Patti Series

Inspired by Italian Elegance. Designed for Singapore Homes.